There are four activities on the critical path,and they have standard deviations of 1,2,4,and 2 days The standard deviation of the critical path is:


A) 3 days
B) 5 days
C) 9 days
D) 16 days
E) 25 days

F) A) and E)
G) A) and B)

Correct Answer

verifed

verified

A Gantt chart of a project shows the scheduled start and finish times for activities

A) True
B) False

Correct Answer

verifed

verified

-What is the estimated standard deviation in the time for activity Z?


A) 2 days
B) 3 days
C) 4 days
D) 8 days
E) 5 days

F) C) and D)
G) B) and D)

Correct Answer

verifed

verified

The slack for path A-D-H-I is:


A) 0
B) 3
C) 4
D) 7
E) 8

F) C) and E)
G) C) and D)

Correct Answer

verifed

verified

There is currently no method that permits activities and their immediate predecessors to overlap

A) True
B) False

Correct Answer

verifed

verified

In crashing a project,a manager will generally focus on activities which:


A) are not on the critical path
B) are the least costly to crash
C) are costly to crash and are on the critical path
D) are on the critical path and are the least costly to crash
E) None of the above

F) C) and E)
G) B) and D)

Correct Answer

verifed

verified

The critical path for the network shown is:


A) A-E-H
B) B-H
C) A-D-G
D) C-F-H
E) C-I-J

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

The duration of the critical path is:


A) 11 days
B) 20 days
C) 18 days
D) 22 days
E) 15 days

F) None of the above
G) C) and E)

Correct Answer

verifed

verified

PERT/Cost:


A) finds the penalty costs if a project is not completed on time
B) compares the actual budget with the planned budget
C) shows management where to focus attention during the project
D) a and b only
E) b and c only

F) D) and E)
G) B) and E)

Correct Answer

verifed

verified

What is the probability that this project will be completed within 205 days?


A) 0 6826
B) 0 8413
C) 0 9544
D) 0 9772
E) 0 9987

F) A) and D)
G) A) and E)

Correct Answer

verifed

verified

Projects involve routine activities that are performed repeatedly

A) True
B) False

Correct Answer

verifed

verified

A manager has decided that an activity has a pessimistic estimate of 15 days,a most-likely estimate of 6 days,and an optimistic estimate of 3 days The expected duration of this activity is 6 days

A) True
B) False

Correct Answer

verifed

verified

Although PERT and CPM were originally developed for somewhat different types of projects,they are now nearly identical in terms of analysis and procedures

A) True
B) False

Correct Answer

verifed

verified

PERT/Cost is a systematic procedure to help a project manager bid on a project

A) True
B) False

Correct Answer

verifed

verified

In PERT,the path with the fewest activities is referred to as the critical path

A) True
B) False

Correct Answer

verifed

verified

At which point does crashing of a project cease?


A) When the project is completed
B) When no additional crashing is possible
C) When the cost to crash equals or exceeds the benefit of crashing
D) All of the above
E) None of the above

F) A) and D)
G) None of the above

Correct Answer

verifed

verified

An activity in a project network cannot begin until all of the activities leading into that activity have been completed

A) True
B) False

Correct Answer

verifed

verified

The sum of durations of the longest path in a project network indicates expected project completion time,and the activities are the critical activities

A) True
B) False

Correct Answer

verifed

verified

-What is the estimated slack time for activity D?


A) 0 days
B) 30 days
C) 40 days
D) 50 days
E) 100 days

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

The earliest finish time for an activity is equal to the latest finish time minus the duration of the activity

A) True
B) False

Correct Answer

verifed

verified

Showing 41 - 60 of 92