Filters
Question type

Study Flashcards

In the lean philosophy, the larger the lot size, the easier it is to schedule.

A) True
B) False

Correct Answer

verifed

verified

Lean systems often use layouts that are based on group technology product requirements.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not a benefit of small lot sizes in lean systems?


A) In-process inventory is considerably less.
B) Each product is produced less frequently.
C) Carrying costs are reduced.
D) There is less clutter in the workplace.
E) Inspection and rework costs are less.

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

In the lean approach, inventories are reduced gradually, instead of eliminating inventories as rapidly as possible.

A) True
B) False

Correct Answer

verifed

verified

True

The ultimate objective in a lean system is:


A) low to moderate levels of inventory.
B) high quality, zero defects.
C) minimal waste (less than 6 percent) .
D) balanced and rapid flow.
E) all of these.

F) C) and D)
G) All of the above

Correct Answer

verifed

verified

If a firm's product mix is 60 percent of product A and 20 percent each of products B and C, an optimal mix-model production schedule would be successive sequences of AAABC.

A) True
B) False

Correct Answer

verifed

verified

False

The small lot-sizing policy works well in a situation where both holding costs and setup costs are high.

A) True
B) False

Correct Answer

verifed

verified

With regard to suppliers, lean systems typically involve:


A) delivery of large lots on short notice
B) the highest quality at the lowest price
C) long-term relationships
D) multiple suppliers to assure continuous availability
E) dedicated staging areas for material

F) None of the above
G) B) and C)

Correct Answer

verifed

verified

Previously, management calculated the number of kanban cards allowed by using a value of 1.3 for X. Assuming nothing else (e.g., usage rates, container capacities, etc.) , which of the following values for X would indicate management's belief that the system has become more efficient?


A) 2.6
B) 2.3
C) 1.5
D) 1.4
E) 1.2

F) A) and B)
G) A) and E)

Correct Answer

verifed

verified

E

The use of small lot sizes in lean operations is in conflict with the EOQ approach since setup costs tend to be significantly higher than holding costs.

A) True
B) False

Correct Answer

verifed

verified

Which of the following questions is not answered by value stream mapping?


A) Where does waste occur?
B) Which processes or subprocesses exhibit the most variability?
C) Where are the best opportunities to extract more value from customers?
D) Where are process bottlenecks?
E) Where do errors occur?

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

Which of the following is not something commonly found in lean systems? (I) Waste reduction (II) Output match to a detailed forecast (III) Visual controls (IV) Quick changeovers (V) Long production runs


A) both I and V
B) both II and V
C) both II and IV
D) both IV and V
E) both III and V

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

A real advantage of the lean philosophy is the reduction of coordination effort required.

A) True
B) False

Correct Answer

verifed

verified

The goal of lean operations is to produce output using fewer resources than traditional planning systems.

A) True
B) False

Correct Answer

verifed

verified

Engineering changes should not be made in the six-month period following the introduction of a new product.

A) True
B) False

Correct Answer

verifed

verified

Process design that supports lean does not include:


A) production flexibility.
B) duplicate facilities.
C) setup time reduction.
D) minimal inventory storage.
E) small lot sizes.

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

The Four Star Publishing Company uses 60 reams of paper each hour at one of its high-speed printing stations. The cycle time for a standard container, which holds 15 reams of paper, averages 40 minutes. If management has decided to use three containers, what efficiency factor was applied?

Correct Answer

verifed

verified

A benefit of lean systems is that lead times are increased, allowing more time for processing.

A) True
B) False

Correct Answer

verifed

verified

One major difference between the use of kanban and MRP in scheduling the products to be built is that kanban is primarily a manual system while MRP uses computers.

A) True
B) False

Correct Answer

verifed

verified

Kanban is the Japanese term for autonomation.

A) True
B) False

Correct Answer

verifed

verified

Showing 1 - 20 of 87

Related Exams

Show Answer