Filters
Question type

Study Flashcards

Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:  Process Time (Hours)  Job  Center A  Center B W45X66Y12Z52\begin{array} { c } \quad\quad\quad{ \text { Process Time (Hours) } } \\\begin{array} { l c c } \text { Job } & \text { Center A } & \text { Center B } \\\hline \mathrm { W } & 4 & 5 \\\mathrm { X } & 6 & 6 \\\mathrm { Y } & 1 & 2 \\\mathrm { Z } & 5 & 2\end{array}\end{array} In developing the sequence which will minimize throughput time, where should job X be placed?

Correct Answer

verifed

verified

Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:  Process Time (Hours)  Job  Center A  Center B W45X66Y12Z52\begin{array} { c } \quad\quad\quad{ \text { Process Time (Hours) } } \\\begin{array} { l c c } \text { Job } & \text { Center A } & \text { Center B } \\\hline \mathrm { W } & 4 & 5 \\\mathrm { X } & 6 & 6 \\\mathrm { Y } & 1 & 2 \\\mathrm { Z } & 5 & 2\end{array}\end{array} If these jobs were scheduled in the sequence shown, what would be the throughput time?

Correct Answer

verifed

verified

Sequencing is concerned with the order in which jobs are done, while loading is concerned with assigning jobs to work centers or workstations.

A) True
B) False

Correct Answer

verifed

verified

The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows:  Project (Hours)   Consultant  A  B  C  D  Charlie 13161113 Betty 11151418 Johnny 15221215 Rick 17171222\begin{array} { c } \quad \quad \quad \quad \quad { \text { Project (Hours) } } \\\begin{array} { l c c c c } \text { Consultant } & \text { A } & \text { B } & \text { C } & \text { D } \\\hline \text { Charlie } & 13 & 16 & 11 & 13 \\\text { Betty } & 11 & 15 & 14 & 18 \\\text { Johnny } & 15 & 22 & 12 & 15 \\\text { Rick } & 17 & 17 & 12 & 22\end{array}\end{array} After the row and column reductions, what is the reduced time for assigning Rick to project D?


A) 0 hours
B) 8 hours
C) 10 hours
D) 9 hours
E) 22 hours

F) None of the above
G) A) and B)

Correct Answer

verifed

verified

Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived:  Job  Processing  Time ( hrs )  Due  (hrs from now)   V 35 W 11X49Y23Z57\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time } ( \text { hrs } ) \end{array} & \begin{array} { c } \text { Due } \\\text { (hrs from now) }\end{array} \\\hline \text { V } & 3 & 5 \\\text { W } & 1 & 1 \\\mathrm { X } & 4 & 9 \\\mathrm { Y } & 2 & 3 \\\mathrm { Z } & 5 & 7\end{array} If Eva uses the first come, first served priority rule to schedule these jobs, what will be the average completion time?


A) 3 hours
B) 5 hours
C) 7 hours
D) 7.2 hours
E) 8 hours

F) B) and C)
G) C) and E)

Correct Answer

verifed

verified

There are four resources and four jobs to be done. The time required for each resource to do each job is as follows:  Job (Hours)   Resource ABCD15877249593698747669\begin{array} { c } \quad \quad \quad \quad { \text { Job (Hours) } } \\\begin{array} { l c c c c } \text { Resource } & \mathrm { A } & \mathrm { B } & \mathrm { C } & \mathrm { D } \\\hline 1 & 5 & 8 & 7 & 7 \\2 & 4 & 9 & 5 & 9 \\3 & 6 & 9 & 8 & 7 \\4 & 7 & 6 & 6 & 9\end{array}\end{array} After the row and column reductions, what is the minimum number of lines needed to cover all of the zeroes?


A) 0 lines
B) 1 line
C) 2 lines
D) 3 lines
E) 4 lines

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

The priority rule where jobs are processed according to the smallest ratio of due date to processing time is:


A) CR.
B) EEDD.
C) FCFS.
D) S/O.
E) SPT.

F) D) and E)
G) B) and C)

Correct Answer

verifed

verified

In a single work center, makespan improvement can be accomplished by selecting the optimal sequencing rule.

A) True
B) False

Correct Answer

verifed

verified

Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived:  Job  Processing  Time (hrs)   Due  (hrs from now)  V35 W11X49Y23Z57\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time (hrs) }\end{array} & \begin{array} { c } \text { Due } \\\text { (hrs from now) }\end{array} \\\hline \mathrm { V } & 3 & 5 \\\mathrm {~W} & 1 & 1 \\\mathrm { X } & 4 & 9 \\\mathrm { Y } & 2 & 3 \\\mathrm { Z } & 5 & 7\end{array} If Eva uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average completion time?


A) 3 hours
B) 5 hours
C) 7 hours
D) 7.2 hours
E) 8 hours

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

Given the information in the table, determine the following: (A) Processing sequence using (1) SPT and (2) EDD (B) Average completion time and average job tardiness using (1) SPT and (2) EDD  Job  Processing  Time (hrs)  Hour  Due  A 1715 B 1025 C 520 D 732 E 1138\begin{array} { ccc } \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time (hrs) }\end{array} & \begin{array} { c } \text { Hour } \\\text { Due }\end{array} \\\hline \text { A } & 17 & 15 \\\text { B } & 10 & 25 \\\text { C } & 5 & 20 \\\text { D } & 7 & 32 \\\text { E } & 11 & 38\end{array}

Correct Answer

verifed

verified

(A) (1) C-D-B-E-A; (2) A-C-B-D-E
(B) SPT...

View Answer

Makespan is the total time needed to complete a group of jobs.

A) True
B) False

Correct Answer

verifed

verified

Job X, which has a duration of four days, is due by the close of business on Friday, December 23. Without looking at the work already scheduled on X's required resource, the scheduler schedules X to be begun on the morning of Tuesday, December 20. This is an example of:


A) infinite scheduling.
B) finite scheduling.
C) forward scheduling.
D) backward scheduling.
E) prioritization.

F) None of the above
G) D) and E)

Correct Answer

verifed

verified

The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:  Job  Processing  Due  Time (hrs)   (hrs from now)  W44X35Y22Z11\begin{array} { l c c } \text { Job } & \text { Processing } & \text { Due } \\\text { Time (hrs) } & \text { (hrs from now) } \\\hline \mathrm { W } & 4 & 4 \\\mathrm { X } & 3 & 5 \\\mathrm { Y } & 2 & 2 \\\mathrm { Z } & 1 & 1\end{array} If he uses the earliest due date first priority rule to schedule these jobs, what will be the average job tardiness?


A) 0 hours
B) 1.5 hours
C) 1.75 hours
D) 2 hours
E) 2.25 hours

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):  Job  Processing Time ( days ) Due Date  (days from now) A22 B56C610D34E48\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing Time } \\( \text { days } )\end{array} & \begin{array} { c } \text { Due Date } \\\text { (days from now) }\end{array} \\\hline \mathrm { A } & 2 & 2 \\\mathrm {~B} & 5 & 6 \\\mathrm { C } & 6 & 10 \\\mathrm { D } & 3 & 4 \\\mathrm { E } & 4 & 8\end{array} What is the average completion time for the first come, first served priority rule schedule? Average job tardiness? Average number of jobs at the center?

Correct Answer

verifed

verified

11.6 days;...

View Answer

Which of the following is critical to effective yield management?


A) one-price pricing
B) forecasting
C) capacity flexibility
D) constant demand
E) trained service personnel

F) All of the above
G) D) and E)

Correct Answer

verifed

verified

Ensuring that the constraining resource is used to its maximum is an example of constraint:


A) elevation.
B) subordination.
C) identification.
D) elimination.
E) exploitation.

F) B) and D)
G) A) and C)

Correct Answer

verifed

verified

The two different approaches to load work centers in job-shop scheduling are:


A) load charts and schedule charts.
B) Gantt charts and assignment method.
C) infinite loading and finite loading.
D) linear programming and makespan.
E) infinite charting and finite charting.

F) B) and E)
G) All of the above

Correct Answer

verifed

verified

In the decision-making hierarchy, scheduling decisions are the final step in the transformation process before actual output occurs.

A) True
B) False

Correct Answer

verifed

verified

Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):  Job  Processing Time ( days ) Due Date  (days from now) A22 B56C610D34E48\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing Time } \\( \text { days } )\end{array} & \begin{array} { c } \text { Due Date } \\\text { (days from now) }\end{array} \\\hline \mathrm { A } & 2 & 2 \\\mathrm {~B} & 5 & 6 \\\mathrm { C } & 6 & 10 \\\mathrm { D } & 3 & 4 \\\mathrm { E } & 4 & 8\end{array} What is the schedule sequence using the shortest processing time priority rule?

Correct Answer

verifed

verified

Priority rules are used in low-volume systems to identify an optimal processing sequence.

A) True
B) False

Correct Answer

verifed

verified

Showing 61 - 80 of 134

Related Exams

Show Answer