What is the standard time (ST) for this task if the employee worked at a fifty percent faster pace than is average,and an allowance of ten percent of the workday is used?


A) 90 seconds
B) 99 seconds
C) 100 seconds
D) 168.8 seconds
E) 150 seconds

F) A) and D)
G) C) and E)

Correct Answer

verifed

verified

All of the following are a part of the basic procedure for methods analysis EXCEPT:


A) identify the job to be studied.
B) gather pertinent facts about the worker, tasks and administrative factors.
C) negotiate wage for completing the work.
D) question present method and propose a new method.

E) None of the above
F) All of the above

Correct Answer

verifed

verified

Methods analysis focuses on which aspect of job design?


A) Behavioural aspects
B) Efficiency aspects
C) Pay levels
D) All of the choices
E) None of the choices

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

Job enlargement represents vertical loading of a job,increasing the level of skills and responsibilities associated with the original job.

A) True
B) False

Correct Answer

verifed

verified

The standard time for a job is determined based on the observed time,a performance rating,and an allowance factor.

A) True
B) False

Correct Answer

verifed

verified

Job enrichment involves an increase in the level of employee responsibility for planning,execution,and control of a job.

A) True
B) False

Correct Answer

verifed

verified

Although quality may be considered in compensation,quantity is always more important.

A) True
B) False

Correct Answer

verifed

verified

Given the following work sampling data, based upon 100 random observations of a particular worker: Given the following work sampling data, based upon 100 random observations of a particular worker:    -For a confidence level of 86.64%,what is the maximum error of the estimate for activity A?  B?  C? -For a confidence level of 86.64%,what is the maximum error of the estimate for activity A? B? C?

Correct Answer

verifed

verified

What is the observed time (OT) for this task?


A) 81 seconds
B) 90 seconds
C) 99 seconds
D) 108 seconds
E) 540 seconds

F) B) and D)
G) C) and E)

Correct Answer

verifed

verified

Which of the following is not an objective of job design?


A) Productivity
B) Safety
C) Quality of work life
D) Line balancing
E) All of the choices are objectives

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

What will be the effect of increasing the maximum acceptance error proportion on sample size in work sampling?


A) Increase in the number of observations needed
B) Decrease in the number of observations needed
C) No effect on sample size
D) Sometimes increase and sometimes decrease in the sample size, depending on the analyst
E) Impossible to say without additional information

F) B) and D)
G) B) and E)

Correct Answer

verifed

verified

A work sampling study does not involve measuring the amount of time to complete different categories of work activities.

A) True
B) False

Correct Answer

verifed

verified

What is the standard time (ST) for this task if the employee worked at a twenty percent faster pace than is average,and an allowance of twenty-five percent of job time is used?


A) 20 seconds
B) 25 seconds
C) 26.7 seconds
D) 30 seconds
E) 32 seconds

F) C) and E)
G) A) and C)

Correct Answer

verifed

verified

Work sampling provides a detailed elemental breakdown of a task for purposes of establishing reliable time standards.

A) True
B) False

Correct Answer

verifed

verified

How many observations should be made if she wants to be 95.44 percent confident that the maximum error in the observed time is two seconds? The standard deviation of task times is 6 seconds.


A) 5
B) 6
C) 30
D) 36
E) 49

F) B) and C)
G) B) and E)

Correct Answer

verifed

verified

What is the normal time (NT) for this task if the employee worked at a fifty percent faster pace than the average?


A) 45 seconds
B) 60 seconds
C) 90 seconds
D) 135 seconds
E) 180 seconds

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

Job enlargement involves an increase in the level of employee responsibility for planning and coordinating tasks.

A) True
B) False

Correct Answer

verifed

verified

In a stopwatch time study,the average time it takes a given worker to perform a task a certain number of times is the:


A) observed time.
B) normal time.
C) standard time.
D) allowance time.
E) performance rating time.

F) B) and C)
G) C) and D)

Correct Answer

verifed

verified

The methods analysis chart which describes the portions of a work cycle during which an operator and equipment are busy or idle is a(n) :


A) process chart.
B) worker-machine chart.
C) gang process chart.
D) simultaneous motion (simo) chart.
E) efficiency/time-of-day chart.

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

What is the standard time (ST) for this task if the bartender worked at a twenty percent faster pace than is average,and an allowance of twenty percent of the workday is used?


A) 112.5 seconds
B) 120 seconds
C) 135 seconds
D) 144 seconds
E) 150 seconds

F) C) and D)
G) All of the above

Correct Answer

verifed

verified