Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)  time for project completion? A)  100 days B)  140 days C)  199 days D)  200 days E)  440 days What is the estimated expected (mean) time for project completion?


A) 100 days
B) 140 days
C) 199 days
D) 200 days
E) 440 days

F) A) and E)
G) All of the above

Correct Answer

verifed

verified

In "crashing" a project, a manager will generally focus on activities which:


A) are not on the critical path.
B) are the least costly to crash.
C) are costly to crash and are on the critical path.
D) are on the critical path and are the least costly to crash.
E) are the easiest to crash.

F) C) and D)
G) A) and D)

Correct Answer

verifed

verified

Deterministic networks use three time estimates-shortest, most likely, and longest-for each activity in order to best determine the activity's estimated time.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)  time for project completion? A)  135 days B)  145 days C)  170 days D)  180 days E)  255 days What is the estimated expected (mean) time for project completion?


A) 135 days
B) 145 days
C) 170 days
D) 180 days
E) 255 days

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified

Given this information about activity 3-4: ES = 10, EF = 15, LS = 16, and LF = 21, we can determine that the amount of slack associated with the activity is:


A) 0.
B) 1.
C) 5.
D) 6.
E) 11.

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified

A hierarchical listing of what must be done during a project is called matrix.

A) True
B) False

Correct Answer

verifed

verified

Matrix organizations transfer control of workers to project managers for the duration of the project.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)  time for activity E? A)  31 weeks B)  38 weeks C)  39 weeks D)  40 weeks E)  43 weeks What is the estimated expected (mean) time for activity E?


A) 31 weeks
B) 38 weeks
C) 39 weeks
D) 40 weeks
E) 43 weeks

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

A node has one entering activity, a, and two leaving activities, b and c. Given the following information, determine the latest starting time for activity a: EFb = 15, EFc = 17, LFb = 24, LFc = 27; activity times are a = 4, b = 6, c = 8.


A) 14
B) 15
C) 16
D) 17
E) 18

F) None of the above
G) B) and D)

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the probability that the critical path for this project will be completed within 52 weeks? A)  0.1554 B)  0.3108 C)  0.3466 D)  0.6554 E)  0.8277 What is the probability that the critical path for this project will be completed within 52 weeks?


A) 0.1554
B) 0.3108
C) 0.3466
D) 0.6554
E) 0.8277

F) A) and E)
G) B) and D)

Correct Answer

verifed

verified

If two consecutive activities have shared slack, this means that each of them can use only half of the slack without delaying completion of the project.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the probability that the critical path for this project will be completed within 210 days? A)  0.5000 B)  0.8413 C)  0.9544 D)  0.9772 E)  0.9987 What is the probability that the critical path for this project will be completed within 210 days?


A) 0.5000
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)  time for project completion? A)  35 weeks B)  39 weeks C)  50 weeks D)  104 weeks E)  105 weeks What is the estimated expected (mean) time for project completion?


A) 35 weeks
B) 39 weeks
C) 50 weeks
D) 104 weeks
E) 105 weeks

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

Which of the following are advantages of PERT and CPM? (I) It is visual. (II) It is automatically updated. (III) Activities that need to be watched closely can be identified.


A) I and II
B) II and III
C) III only
D) I and III
E) I, II, and III

F) A) and E)
G) C) and D)

Correct Answer

verifed

verified

The project management strategy of injecting additional resources in order to reduce the length of the project is called:


A) expediting.
B) rushing.
C) panicking.
D) crashing.
E) loading.

F) B) and D)
G) C) and E)

Correct Answer

verifed

verified

A Gantt chart is a popular visual tool for displaying the established precedence relationships.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)  time for activity E? A)  91 days B)  99 days C)  100 days D)  101 days E)  115 days What is the estimated expected (mean) time for activity E?


A) 91 days
B) 99 days
C) 100 days
D) 101 days
E) 115 days

F) A) and E)
G) D) and E)

Correct Answer

verifed

verified

A popular visual tool for planning and scheduling simple projects, and for monitoring progress, is the:


A) activity-on-arrows network.
B) activity-on-nodes network.
C) Gantt chart.
D) critical path method.
E) program evaluation and review technique.

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

The project computing algorithm requires both a forward and a backward pass.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)  time for activity E? A)  35 days B)  36 days C)  39 days D)  40 days E)  45 days What is the estimated expected (mean) time for activity E?


A) 35 days
B) 36 days
C) 39 days
D) 40 days
E) 45 days

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified