Filters
Question type

Study Flashcards

Scheduling in service systems may involve scheduling: (I) the workforce. (II) the equipment. (III) customers.


A) II only
B) I and II only
C) II and III only
D) I and III only
E) I, II, and III

F) C) and D)
G) D) and E)

Correct Answer

verifed

verified

Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived: Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived:   If Eva uses the earliest due date first (EDD)  priority rule to schedule these jobs, what will be the average job tardiness? A)  2 hours B)  2.2 hours C)  2.33 hours D)  2.4 hours E)  3 hours If Eva uses the earliest due date first (EDD) priority rule to schedule these jobs, what will be the average job tardiness?


A) 2 hours
B) 2.2 hours
C) 2.33 hours
D) 2.4 hours
E) 3 hours

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

A Gantt chart is a basic scheduling tool that is most useful in low-volume systems.

A) True
B) False

Correct Answer

verifed

verified

Sequencing is concerned with the order in which jobs are done, while loading is concerned with assigning jobs to work centers or workstations.

A) True
B) False

Correct Answer

verifed

verified

Scheduled due dates are the result of:


A) promises to customers.
B) MRP processing.
C) managerial decisions.
D) all of the choices.
E) our competitor's promises.

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

Which of the following is the last step in the capacity/scheduling chain?


A) product planning
B) process planning
C) capacity planning
D) aggregate planning
E) scheduling

F) None of the above
G) A) and E)

Correct Answer

verifed

verified

Bottlenecks in service systems may shift with the passage of time, so that different operations become bottleneck operations at different times.

A) True
B) False

Correct Answer

verifed

verified

Scheduling in service systems often takes the form of: (I) appointment systems. (II) reservation systems. (III) makespan systems.


A) I only
B) II only
C) I and II only
D) III only
E) I, II, and III

F) All of the above
G) B) and D)

Correct Answer

verifed

verified

The priority rule which will sequence jobs in the order they are received is:


A) EDD.
B) LIFO.
C) SPT.
D) CR.
E) FCFS.

F) A) and C)
G) C) and E)

Correct Answer

verifed

verified

Job X, which has a duration of four days, is due by the close of business on Friday, December 23. Without looking at the work already scheduled on X's required resource, the scheduler schedules X to be begun on the morning of Tuesday, December 20. This is an example of:


A) infinite scheduling.
B) finite scheduling.
C) forward scheduling.
D) backward scheduling.
E) prioritization.

F) C) and E)
G) A) and E)

Correct Answer

verifed

verified

The elimination of idle time on both bottleneck and non-bottleneck operations must be accomplished to optimize output.

A) True
B) False

Correct Answer

verifed

verified

The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:  Job  Processing Time  (hrs)   Due  (hrs from now)   W 44 X 35 Y 22 Z 11\begin{array} { c c c } \hline \text { Job } & \begin{array} { c } \text { Processing Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Due } \\\text { (hrs from now) }\end{array} \\\text { W } & 4 & 4 \\\text { X } & 3 & 5 \\\text { Y } & 2 & 2 \\\text { Z } & 1 & 1\end{array} If he uses the earliest due date first priority rule to schedule these jobs, what will be the average job tardiness?


A) 0 hours
B) 1.5 hours
C) 1.75 hours
D) 2 hours
E) 2.25 hours

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

Splitting a large lot after one operation beyond a bottleneck operation would reduce the overall waiting time of the bottleneck operation.

A) True
B) False

Correct Answer

verifed

verified

In the decision-making hierarchy, scheduling decisions are the final step in the transformation process before actual output occurs.

A) True
B) False

Correct Answer

verifed

verified

The output of the system cannot exceed the output of the bottleneck operation(s).

A) True
B) False

Correct Answer

verifed

verified

For the jobs listed below, which processing sequence would result using Johnson's rule? For the jobs listed below, which processing sequence would result using Johnson's rule?   A)  c-a-d-b B)  b-d-a-c C)  a-b-c-d D)  d-c-b-a E)  c-a-b-d


A) c-a-d-b
B) b-d-a-c
C) a-b-c-d
D) d-c-b-a
E) c-a-b-d

F) B) and E)
G) None of the above

Correct Answer

verifed

verified

The two different approaches to load work centers in job-shop scheduling are:


A) load charts and schedule charts.
B) Gantt charts and assignment method.
C) infinite loading and finite loading.
D) linear programming and makespan.
E) infinite charting and finite charting.

F) A) and D)
G) C) and E)

Correct Answer

verifed

verified

To facilitate utilization of bottleneck operations, in theory of constraints scheduling ________ can be split into __________ to reduce waiting times.


A) bottleneck lots; nonbottleneck lots
B) transfer batches; process lots
C) sized lots; constrained lots
D) process batches; transfer batches
E) buffer lots; transfer lots

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

There are four resources and four jobs to be done. Assume there must be one-to-one matching between jobs and resources. The time required for each resource to do each job is as follows:  Job (Hours)   Resource  A  B  C  D 15877249593698747669\begin{array} { c c c c c } & { \text { Job (Hours) } } \\\text { Resource } & \text { A } & \text { B } & \text { C } & \text { D } \\1 & 5 & 8 & 7 & 7 \\2 & 4 & 9 & 5 & 9 \\3 & 6 & 9 & 8 & 7 \\4 & 7 & 6 & 6 & 9\end{array} For the optimal schedule, what is the total number of hours required to complete these jobs?


A) 23 hours
B) 22 hours
C) 21 hours
D) 20 hours
E) 19 hours

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:  Job  Processing Time  (hrs)   Due  (hrs from now)   W 44X35Y22Z11\begin{array} { c c c } \text { Job } & \begin{array} { c } \text { Processing Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Due } \\\text { (hrs from now) }\end{array} \\\text { W } & 4 & 4 \\\mathrm { X } & 3 & 5 \\\mathrm { Y } & 2 & 2 \\\mathrm { Z } & 1 & 1\end{array} If he uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in his shop today?


A) 0
B) 1
C) 2
D) 3
E) 4

F) C) and E)
G) B) and D)

Correct Answer

verifed

verified

Showing 41 - 60 of 98

Related Exams

Show Answer