Correct Answer
verified
Multiple Choice
A) $134.79
B) $141.89
C) $149.36
D) $164.29
E) $205.36
Correct Answer
verified
Multiple Choice
A) 1.91 years
B) 2.12 years
C) 2.36 years
D) 2.59 years
E) 2.85 years
Correct Answer
verified
Multiple Choice
A) More of Project A's cash flows occur in the later years.
B) More of Project B's cash flows occur in the later years.
C) We must have information on the cost of capital in order to determine which project has the larger early cash flows.
D) The NPV profile graph is inconsistent with the statement made in the problem.
E) The crossover rate, i.e., the rate at which Projects A and B have the same NPV, is greater than either project's IRR.
Correct Answer
verified
Multiple Choice
A) $24.14
B) $26.82
C) $29.80
D) $33.11
E) $36.42
Correct Answer
verified
Multiple Choice
A) If Project A has a higher IRR than Project B, then Project A must have the lower NPV.
B) If Project A has a higher IRR than Project B, then Project A must also have a higher NPV.
C) The IRR calculation implicitly assumes that all cash flows are reinvested at the WACC.
D) The IRR calculation implicitly assumes that cash flows are withdrawn from the business rather than being reinvested in the business.
E) If a project has normal cash flows and its IRR exceeds its WACC, then the project's NPV must be positive.
Correct Answer
verified
Multiple Choice
A) $11.45
B) $12.72
C) $14.63
D) $16.82
E) $19.35
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 1.61 years
B) 1.79 years
C) 1.99 years
D) 2.22 years
E) 2.44 years
Correct Answer
verified
Multiple Choice
A) $32.12
B) $35.33
C) $38.87
D) $40.15
E) $42.16
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Project D probably has a higher IRR.
B) Project D is probably larger in scale than Project C.
C) Project C probably has a faster payback.
D) Project C probably has a higher IRR.
E) The crossover rate between the two projects is below 12%.
Correct Answer
verified
Multiple Choice
A) The longer a project's payback period, the more desirable the project is normally considered to be by this criterion.
B) One drawback of the regular payback for evaluating projects is that this method does not properly account for the time value of money.
C) If a project's payback is positive, then the project should be rejected because it must have a negative NPV.
D) The regular payback ignores cash flows beyond the payback period, but the discounted payback method overcomes this problem.
E) If a company uses the same payback requirement to evaluate all projects, say it requires a payback of 4 years or less, then the company will tend to reject projects with relatively short lives and accept long-lived projects, and this will cause its risk to increase over time.
Correct Answer
verified
Multiple Choice
A) For a project to have more than one IRR, then both IRRs must be greater than the WACC.
B) If two projects are mutually exclusive, then they are likely to have multiple IRRs.
C) If a project is independent, then it cannot have multiple IRRs.
D) Multiple IRRs can occur only if the signs of the cash flows change more than once.
E) If a project has two IRRs, then the smaller one is the one that is most relevant, and it should be accepted and relied upon.
Correct Answer
verified
Multiple Choice
A) 2.31 years
B) 2.56 years
C) 2.85 years
D) 3.16 years
E) 3.52 years
Correct Answer
verified
Multiple Choice
A) A project's IRR increases as the WACC declines.
B) A project's NPV increases as the WACC declines.
C) A project's MIRR is unaffected by changes in the WACC.
D) A project's regular payback increases as the WACC declines.
E) A project's discounted payback increases as the WACC declines.
Correct Answer
verified
Multiple Choice
A) Lacks an objective, market-determined benchmark for making decisions.
B) Ignores cash flows beyond the payback period.
C) Does not directly account for the time value of money.
D) Does not provide any indication regarding a project's liquidity or risk.
E) Does not take account of differences in size among projects.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The IRR method appeals to some managers because it gives an estimate of the rate of return on projects rather than a dollar amount, which the NPV method provides.
B) The discounted payback method eliminates all of the problems associated with the payback method.
C) When evaluating independent projects, the NPV and IRR methods often yield conflicting results regarding a project's acceptability.
D) To find the MIRR, we discount the TV at the IRR.
E) A project's NPV profile must intersect the X-axis at the project's WACC.
Correct Answer
verified
Multiple Choice
A) $185.90
B) $197.01
C) $208.11
D) $219.22
E) $230.32
Correct Answer
verified
Showing 81 - 100 of 107
Related Exams