Johnson's rule sequences a set of jobs through two different machines or work centers in the same order.

A) True
B) False

Correct Answer

verifed

verified

Eight jobs have been sequenced at a single work center. Total processing time for the eight jobs is 34 hours and total flow time for the sequence is 85 hours. For this schedule, utilization is __________ and average jobs in the system is __________.


A) 100 percent; 10.625
B) low; .0941
C) 0.400 or 40 percent; 2.5
D) 0.235 or 23.5 percent; 4.25
E) maximized; minimized

F) B) and E)
G) C) and D)

Correct Answer

verifed

verified

Delta uses mathematical short-term scheduling techniques and a high-tech nerve center to manage the rapid rescheduling necessary to cope with weather delays and similar disruptions.

A) True
B) False

Correct Answer

verifed

verified

Orders are processed in the sequence in which they arrive if (the) __________ rule sequences the jobs.


A) earliest due date
B) slack time remaining
C) first come, first served
D) critical ratio
E) Johnson's

F) B) and C)
G) None of the above

Correct Answer

verifed

verified

What is input-output control?

Correct Answer

verifed

verified

Input-output control is a tech...

View Answer

Which of the following is not a key benefit from effective scheduling?


A) lower cost
B) faster delivery
C) dependable delivery
D) quality
E) A and D

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Forward scheduling is the scheduling of


A) the end items or finished products
B) jobs as soon as the requirements are known
C) the start items or component parts
D) the final operation first beginning with the due date
E) jobs according to their profit contributions

F) B) and E)
G) A) and C)

Correct Answer

verifed

verified

Earliest due date is a shop floor dispatching (sequencing) rule that relates the time available to complete a job to the amount of work left to be completed.

A) True
B) False

Correct Answer

verifed

verified

Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Sigma before work center Delta. According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs? Five jobs are waiting for processing through two work centers. Their processing time (in minutes)  at each work center is contained in the table below. Each job requires work center Sigma before work center Delta. According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs?   A)  R-S-T-U-V B)  S-V-T-R-U C)  S-U-T-V-R D)  V-R-U-S-T E)  none of the above


A) R-S-T-U-V
B) S-V-T-R-U
C) S-U-T-V-R
D) V-R-U-S-T
E) none of the above

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

The benefits of effective scheduling include lower cost, faster delivery, and dependable delivery.

A) True
B) False

Correct Answer

verifed

verified

What makes short-term scheduling of strategic importance?

Correct Answer

verifed

verified

Effective scheduling lowers cost by maki...

View Answer

Identify the types of planning files used in scheduling decisions. Which are used in manual systems, and which are used in automated systems?

Correct Answer

verifed

verified

The three types are item maste...

View Answer

The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants -- Charlie, Gerald, Johnny, and Rick -- to complete any of the four projects, as follows: The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants -- Charlie, Gerald, Johnny, and Rick -- to complete any of the four projects, as follows:    a. In how many different ways can she assign these consultants to these projects? b. What is the total number of hours required by the following arbitrary assignment? Charlie→B; Gerald→A; Johnny→D; Rick→C c. What is the optimal assignment of consultants to projects? (Use the assignment method; SHOW YOUR WORK!) d. For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects? e. What is the significance, if any, of the fact that Gerald is the best performer at all four projects? a. In how many different ways can she assign these consultants to these projects? b. What is the total number of hours required by the following arbitrary assignment? Charlie→B; Gerald→A; Johnny→D; Rick→C c. What is the optimal assignment of consultants to projects? (Use the assignment method; SHOW YOUR WORK!) d. For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects? e. What is the significance, if any, of the fact that Gerald is the best performer at all four projects?

Correct Answer

verifed

verified

(a) 4!, or 24 ways. (b) 16+13+15+12=56 h...

View Answer

The word "finite" in finite capacity scheduling refers to the use of finite or limited capacity rather than unlimited capacity.

A) True
B) False

Correct Answer

verifed

verified

The production database containing information about each of the components that a firm produces or purchases is the


A) routing file
B) work-center master file
C) control file
D) item master file
E) none of the above

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

A work center is interested in limiting work-in-process by not allowing production to start again until the current batch is finished. The best solution most likely involves


A) MRP
B) ConWIP cards
C) Gantt Charts
D) Johnson's rule
E) Loading

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed?   A)  A, B, C, D, E B)  C, E, A, D, B. C)  B, D, A, E, C D)  D, A, E, B, C E)  C, E, A, D, B


A) A, B, C, D, E
B) C, E, A, D, B.
C) B, D, A, E, C
D) D, A, E, B, C
E) C, E, A, D, B

F) B) and E)
G) C) and D)

Correct Answer

verifed

verified

Identify some scheduling optimization systems that are used at retail stores. Describe what these systems do.

Correct Answer

verifed

verified

Workbrain, Cybershift, and Kro...

View Answer

Three jobs are to be assigned to three machines. Cost for each job-machine combination appears in the table below. Perform the first two steps of the assignment method (subtract the smallest number in each row and subtract the smallest number in each column; then cover with straight lines) . At this point in the problem-solving process Three jobs are to be assigned to three machines. Cost for each job-machine combination appears in the table below. Perform the first two steps of the assignment method (subtract the smallest number in each row and subtract the smallest number in each column; then cover with straight lines) . At this point in the problem-solving process   A)  the row for Job 1 contains the values 5, 6, and 0 B)  calculations are complete, and the problem is ready for an optimal set of assignments C)  the column for Machine B indicates that it should be retired D)  Job 1 should be performed on Machine B E)  Job 1 should be performed on Machine A


A) the row for Job 1 contains the values 5, 6, and 0
B) calculations are complete, and the problem is ready for an optimal set of assignments
C) the column for Machine B indicates that it should be retired
D) Job 1 should be performed on Machine B
E) Job 1 should be performed on Machine A

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified

Gantt charts are useful for scheduling jobs, but not for loading them.

A) True
B) False

Correct Answer

verifed

verified

Showing 21 - 40 of 139