Indirect cost for a project is $2500 per day.Given the following information,determine an optimum crashing plan.What is the total cost for the plan? 11eab92b_c478_ba81_99e6_91c7ca2cb86e

Correct Answer

verifed

verified

CRITICAL PATH = A-C-...

View Answer

A hierarchical listing of what must be done during the project is called:


A) work breakdown structure (WBS) .
B) program evaluation and review technique (PERT) .
C) planning matrix.
D) crashing.
E) critical path method (CPM) .

F) A) and C)
G) B) and D)

Correct Answer

verifed

verified

The Project Manager is about to begin a project comprised of the following six activities: The Project Manager is about to begin a project comprised of the following six activities:   What is the estimated expected (mean) duration for project completion? A) 100 days B) 140 days C) 199 days D) 200 days E) 440 days What is the estimated expected (mean) duration for project completion?


A) 100 days
B) 140 days
C) 199 days
D) 200 days
E) 440 days

F) A) and C)
G) A) and E)

Correct Answer

verifed

verified

What are the estimated slack times (in weeks)for activities A-H? 11eab92b_c478_4546_99e6_bbbc69ea584f

Correct Answer

verifed

verified

The Project Manager is about to begin a project comprised of the following six activities: The Project Manager is about to begin a project comprised of the following six activities:   What is the estimated expected (mean) duration for activity E? A) 91 days B) 99 days C) 100 days D) 101 days E) 115 days What is the estimated expected (mean) duration for activity E?


A) 91 days
B) 99 days
C) 100 days
D) 101 days
E) 115 days

F) B) and E)
G) A) and D)

Correct Answer

verifed

verified

A project superintendent is about to begin work on a freeway resurfacing project,which is comprised of the following five activities: A project superintendent is about to begin work on a freeway resurfacing project,which is comprised of the following five activities:   What is the estimated expected (mean) duration for Activity E? A) 31 weeks B) 38 weeks C) 39 weeks D) 40 weeks E) 43 weeks What is the estimated expected (mean) duration for Activity E?


A) 31 weeks
B) 38 weeks
C) 39 weeks
D) 40 weeks
E) 43 weeks

F) A) and E)
G) C) and E)

Correct Answer

verifed

verified

C

A project has the activities and activity durations (days)listed below.There are two paths: start-A-B-end and start-C-D-finish.Determine the probability that the project will require more than 15 days from start to finish. 11eab92b_c477_f721_99e6_39488dcb3497

Correct Answer

verifed

verified

A Gantt chart provides a visual representation of the sequence of activities in a project.

A) True
B) False

Correct Answer

verifed

verified

The path in a precedence network with the longest duration is the critical path.

A) True
B) False

Correct Answer

verifed

verified

The precedence network for a project depicts sequential relationships among activities in a project.

A) True
B) False

Correct Answer

verifed

verified

True

Although PERT and CPM were originally developed for somewhat different types of projects,they are now nearly identical in terms of analysis and procedures.

A) True
B) False

Correct Answer

verifed

verified

The manager of a National Forest is about to undertake a reforestation project in a burned out area.The project will involve the following six activities: The manager of a National Forest is about to undertake a reforestation project in a burned out area.The project will involve the following six activities:   What is the estimated standard deviation of the duration for activity Z? A) 3 days B) 2 days C) 4 days D) 8 days E) 5 days What is the estimated standard deviation of the duration for activity Z?


A) 3 days
B) 2 days
C) 4 days
D) 8 days
E) 5 days

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

A project manager should not be concerned with the political nature of the organization they are working with.

A) True
B) False

Correct Answer

verifed

verified

Project managers are sometimes able to reduce indirect project costs by increasing direct costs.

A) True
B) False

Correct Answer

verifed

verified

When developing probabilistic estimates of project duration,it is necessary to know which of the following?


A) The mean and variance of every activity
B) The mean and variance of activities on the critical path
C) The standard deviation of activities on the critical path
D) Each activity's probability of completion
E) The distribution of activity durations

F) C) and E)
G) C) and D)

Correct Answer

verifed

verified

A project consists of nine major activities,as shown.There are three separate paths in the network: a-c-f,b-d-g,and e-h-i. (i)What is expected project duration time? (ii)Determine the probability that the project will take more than 35 weeks to complete.(All durations are in weeks.) 11eab92b_c477_d00e_99e6_ad14123209e7

Correct Answer

verifed

verified

11eab92b_c477_d00f_99e6_117677bd3ac7_TB6896_00_TB6896_00 (i)32 wk.(ii)P(Project < 35)= (.9525)(.9082)(.8413)=.728.P(Project > 35)= 1-.728 = .272.

Project planning determines how the project is to be undertaken,and includes breaking the job down into smaller components called task identification.

A) True
B) False

Correct Answer

verifed

verified

Using the information given,do the following: (i)Identify the critical path. (ii)Determine expected project duration. 11eab92b_c477_a8fb_99e6_2fa9612f9262

Correct Answer

verifed

verified

(i)The critical path...

View Answer

In precedence network analysis,knowing the slack time allows managers to:


A) delay critical activities.
B) extent the project if necessary.
C) increase the critical path.
D) pay attention to activities that could delay the project.
E) decrease the project duration.

F) C) and D)
G) A) and D)

Correct Answer

verifed

verified

What is the estimated expected (mean)duration (in weeks)for project completion? 11eab92b_c478_1e35_99e6_957d44b0ca89

Correct Answer

verifed

verified